Kelly Playground Skate Park Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will construct a skate park and reconstruct the amphitheater and basketball courts in Kelly Playground (PS 52).
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: June 2011
Projected Completion Date:
November 2013
Completion Date:
April 2015
Procurement
Start Date: April 2015
Projected Completion Date:
January 2016
Completion
Date:
April 2016
Construction
Start Date: May 2016
Projected Completion Date:
May 2018
Completion Date: July 2018
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
- Mayoral
Location
Al QuiƱones Playground, Bronx
Avenue Saint John between Kelly and Beck Streets
Community Board: 02
Project Staff
Project Liaison: Katerine Borrome
Contact NYC Parks
about this project
Last updated: 01/17/2025