La Plaza Cultural Community Garden Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will construct new steel fencing and gates and reconstruct the curbs at La Plaza Cultural Community Garden.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: February 2018
Projected Completion Date:
December 2018
Completion Date:
December 2018
Procurement
Start Date: September 2018
Projected Completion Date:
February 2019
Completion
Date:
March 2019
Construction
Start Date: April 2019
Projected Completion Date:
July 2019
Completion Date: July 2019
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
Last updated: 11/22/2024