La Plaza Cultural Community Garden Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct new steel fencing and gates and reconstruct the curbs at La Plaza Cultural Community Garden.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: February 2018
Projected Completion Date: December 2018
Completion Date: December 2018

Procurement

Start Date: September 2018
Projected Completion Date: February 2019
Completion Date: March 2019

Construction

Start Date: April 2019
Projected Completion Date: July 2019
Completion Date: July 2019

Understand how we build parks.

Funding

Total Funding: $238,000
Funding Sources:
  • Borough President
  • City Council

Location

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 11/22/2024