Riverside Park 102nd Street Field House Water Service Installation

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will install a new water service line to the 102nd street field house in Riverside Park

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: March 2018
Projected Completion Date: December 2017
Completion Date: July 2018

Procurement

Start Date: April 2018
Projected Completion Date: September 2018
Completion Date: June 2018

Construction

Start Date: July 2018
Projected Completion Date: December 2018
Completion Date: January 2019

Understand how we build parks.

Funding

Total Funding: $183,000
Funding Sources:
  • Mayoral
  • Borough President

Location

Riverside Park, Manhattan

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project