This project will install new interior plumbing systems for the field house adjacent to West 102nd Street in Riverside Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: November 2018
Projected Completion Date: January 2018
Completion Date: November 2018

Procurement

Start Date: May 2018
Projected Completion Date: October 2018
Completion Date: August 2018

Construction

Start Date: January 2019
Projected Completion Date: May 2019
Completion Date: November 2019

Understand how we build parks.

Funding

Total Funding: $228,000
Funding Source: Mayoral

Location