West 102nd Street Riverside Park Field House Interior Plumbing Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will install new interior plumbing systems for the field house adjacent to West 102nd Street in Riverside Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: November 2018
Projected Completion Date:
January 2018
Completion Date:
November 2018
Procurement
Start Date: May 2018
Projected Completion Date:
October 2018
Completion
Date:
August 2018
Construction
Start Date: January 2019
Projected Completion Date:
May 2019
Completion Date: November 2019
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Riverside Park, Manhattan
Project Staff
Project Liaison: Cristin Leoutsakos