Thomas J. Cuite Park Water Service Installation
-
100% complete
-
100% complete
-
100% complete
This project will install new water service to Thomas J. Cuite Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: December 2018
Projected Completion Date:
December 2018
Completion Date:
June 2018
Procurement
Start Date: April 2018
Projected Completion Date:
September 2018
Completion
Date:
June 2018
Construction
Start Date: July 2018
Projected Completion Date:
December 2018
Completion Date: February 2019
Understand how we build parks.
Funding
Funding Sources:
- Mayoral
- Borough President
Location
Thomas J. Cuite Park, Brooklyn
Project Staff
Project Liaison: Cristin Leoutsakos
Contact NYC Parks
about this project