Thomas J. Cuite Park Water Service Installation

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will install new water service to Thomas J. Cuite Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: December 2018
Projected Completion Date: December 2018
Completion Date: June 2018

Procurement

Start Date: April 2018
Projected Completion Date: September 2018
Completion Date: June 2018

Construction

Start Date: July 2018
Projected Completion Date: December 2018
Completion Date: February 2019

Understand how we build parks.

Funding

Total Funding: $80,000
Funding Sources:
  • Mayoral
  • Borough President

Location

Thomas J. Cuite Park, Brooklyn

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 10/11/2024