Brook Park Fence, Water Supply and Sidewalk Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the perimeter fencing, water supply, and portions of the street sidewalk at Brook Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: January 2021
Projected Completion Date: June 2021
Completion Date: July 2021

Procurement

Start Date: July 2021
Projected Completion Date: March 2022
Completion Date: February 2023

Construction

Start Date: April 2023
Projected Completion Date: January 2024
Completion Date: September 2024

Understand how we build parks.

Funding

Total Funding: $994,000
Funding Sources:
  • Borough President
  • City Council

Location

Brook Park, Bronx
Brook Avenue between East 140th Street and East 141st Street
Community Board: 01

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project

Last updated: 11/26/2024