Brook Park Fence, Water Supply and Sidewalk Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the perimeter fencing, water supply, and portions of the street sidewalk at Brook Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: January 2021
Projected Completion Date:
June 2021
Completion Date:
July 2021
Procurement
Start Date: July 2021
Projected Completion Date:
March 2022
Completion
Date:
February 2023
Construction
Start Date: April 2023
Projected Completion Date:
January 2024
Completion Date: September 2024
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
Location
Brook Park, Bronx
Brook Avenue between East 140th Street and East 141st Street
Community Board: 01
Project Staff
Project Liaison: Katerine Borrome
Contact NYC Parks
about this project
Last updated: 11/26/2024