Kissena Corridor Park Path Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct a new asphalt path, reconstruct a lawn and remove a chain link fence in Kissena Corridor Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: June 2015
Projected Completion Date: June 2017
Completion Date: January 2018

Procurement

Start Date: December 2017
Projected Completion Date: May 2018
Completion Date: March 2018

Construction

Start Date: April 2018
Projected Completion Date: April 2018
Completion Date: July 2018

Understand how we build parks.

Funding

Total Funding: $105,000
Funding Source: Mayoral

Location

Kissena Corridor Park, Queens

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 10/11/2024