Sperandeo Playground Sport Courts Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the basketball and handball courts at Sperandeo Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: February 2017
Projected Completion Date: May 2018
Completion Date: May 2018

Procurement

Start Date: May 2017
Projected Completion Date: October 2017
Completion Date: May 2018

Construction

Start Date: July 2018
Projected Completion Date: November 2018
Completion Date: November 2018

Understand how we build parks.

Funding

Total Funding: $299,000
Funding Source: Mayoral

Location

Sperandeo Brothers Playground, Brooklyn

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 10/11/2024