Silver Lake Park Path Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the paths at Silver Lake Park.
Project Timeline
Design
Assigned & Start Date: July 2017
Projected Completion Date:
June 2018
Completion Date:
June 2018
Procurement
Start Date: February 2018
Projected Completion Date:
July 2018
Completion
Date:
June 2018
Construction
Start Date: July 2018
Projected Completion Date:
February 2019
Completion Date: February 2019
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Silver Lake Park, Staten Island
Project Staff
Project Liaison: Joseph Homsey
Contact NYC Parks
about this project
Last updated: 01/17/2025