Silver Lake Park Path Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the paths at Silver Lake Park.

Project Timeline

Design

Assigned & Start Date: July 2017
Projected Completion Date: June 2018
Completion Date: June 2018

Procurement

Start Date: February 2018
Projected Completion Date: July 2018
Completion Date: June 2018

Construction

Start Date: July 2018
Projected Completion Date: February 2019
Completion Date: February 2019

Understand how we build parks.

Funding

Total Funding: $775,000
Funding Source: Mayoral

Location

Silver Lake Park, Staten Island

 

Project Staff

Project Liaison: Joseph Homsey
Contact NYC Parks about this project

Last updated: 01/17/2025