Orchard Beach Nature Center Roof Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the roof at Orchard Beach Nature Center.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: April 2017
Projected Completion Date: July 2017
Completion Date: November 2017

Procurement

Start Date: August 2017
Projected Completion Date: January 2018
Completion Date: October 2017

Construction

Start Date: March 2018
Projected Completion Date: June 2018
Completion Date: July 2018

Understand how we build parks.

Funding

Total Funding: $208,000
Funding Source: Mayoral

Location

Pelham Bay Park, Bronx

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 10/11/2024