Orchard Beach Nature Center Roof Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the roof at Orchard Beach Nature Center.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: April 2017
Projected Completion Date:
July 2017
Completion Date:
November 2017
Procurement
Start Date: August 2017
Projected Completion Date:
January 2018
Completion
Date:
October 2017
Construction
Start Date: March 2018
Projected Completion Date:
June 2018
Completion Date: July 2018
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Pelham Bay Park, Bronx
Project Staff
Project Liaison: Cristin Leoutsakos
Contact NYC Parks
about this project
Last updated: 01/17/2025