Marine Park Veterans Memorial Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the veterans' memorial in Marine Park with new seating, a planting bed around the memorial, and asphalt paving.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: March 2017
Projected Completion Date:
June 2018
Completion Date:
March 2018
Procurement
Start Date: June 2017
Projected Completion Date:
November 2017
Completion
Date:
March 2018
Construction
Start Date: September 2018
Projected Completion Date:
November 2018
Completion Date: October 2018
Understand how we build parks.
Funding
Funding Source: City Council
Location
Marine Park, Brooklyn
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project