Queens Emerald Ash Borer (EAB) Related Tree Removal FY25
-
100% complete
-
0% complete
-
0% complete
This project will remove trees hosted by Emerald Ash Borer (EAB) in Queens
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: September 2024
Projected Completion Date:
January 2025
Completion Date:
November 2024
Procurement
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Last updated: 11/22/2024