Ehrenreich-Austin Playground Public Restroom Building Plumbing System Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the plumbing system of the public restroom building in Ehrenreich-Austin Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: November 2016
Projected Completion Date: May 2017
Completion Date: November 2017

Procurement

Start Date: August 2017
Projected Completion Date: January 2018
Completion Date: October 2017

Construction

Start Date: April 2018
Projected Completion Date: September 2018
Completion Date: January 2019

Understand how we build parks.

Funding

Total Funding: $100,000
Funding Sources:
  • Mayoral
  • City Council

Location

Ehrenreich-Austin Playground, Queens

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 11/22/2024