Ehrenreich-Austin Playground Public Restroom Building Plumbing System Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the plumbing system of the public restroom building in Ehrenreich-Austin Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: November 2016
Projected Completion Date:
May 2017
Completion Date:
November 2017
Procurement
Start Date: August 2017
Projected Completion Date:
January 2018
Completion
Date:
October 2017
Construction
Start Date: April 2018
Projected Completion Date:
September 2018
Completion Date: January 2019
Understand how we build parks.
Funding
Funding Sources:
- Mayoral
- City Council
Location
Ehrenreich-Austin Playground, Queens
Project Staff
Project Liaison: Cristin Leoutsakos
Contact NYC Parks
about this project
Last updated: 11/22/2024