Forest Park Sobelsohn Playground Public Restroom Building Plumbing System Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the plumbing system of the public restroom building in Sobelsohn Playground in Forest Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: November 2016
Projected Completion Date: May 2017
Completion Date: November 2017

Procurement

Start Date: August 2017
Projected Completion Date: January 2018
Completion Date: October 2017

Construction

Start Date: September 2019
Projected Completion Date: June 2020
Completion Date: September 2020

Understand how we build parks.

Funding

Total Funding: $148,000
Funding Sources:
  • Mayoral
  • City Council

Location

Forest Park, Queens

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project