Forest Park Sobelsohn Playground Public Restroom Building Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the public restroom building in Sobelsohn Playground in Forest Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: November 2016
Projected Completion Date:
May 2017
Completion Date:
November 2017
Procurement
Start Date: August 2017
Projected Completion Date:
January 2018
Completion
Date:
October 2017
Construction
Start Date: September 2019
Projected Completion Date:
June 2020
Completion Date: September 2020
Understand how we build parks.
Funding
Funding Sources:
- Mayoral
- City Council
Location
Forest Park, Queens
Project Staff
Project Liaison: Cristin Leoutsakos
Contact NYC Parks
about this project
Last updated: 01/17/2025