Harry Chapin Playground Sprinkler Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will install a new drainage line and hydraulic board activator at Harry Chapin Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: May 2017
Projected Completion Date:
June 2018
Completion Date:
September 2018
Procurement
Start Date: March 2018
Projected Completion Date:
August 2018
Completion
Date:
September 2018
Construction
Start Date: August 2019
Projected Completion Date:
October 2019
Completion Date: November 2019
Understand how we build parks.
Funding
Funding Sources:
- Mayoral
- City Council
Location
Harry Chapin Playground, Brooklyn
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 01/17/2025