Harry Chapin Playground Sprinkler Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will install a new drainage line and hydraulic board activator at Harry Chapin Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: May 2017
Projected Completion Date: June 2018
Completion Date: September 2018

Procurement

Start Date: March 2018
Projected Completion Date: August 2018
Completion Date: September 2018

Construction

Start Date: August 2019
Projected Completion Date: October 2019
Completion Date: November 2019

Understand how we build parks.

Funding

Total Funding: $88,000
Funding Sources:
  • Mayoral
  • City Council

Location

Harry Chapin Playground, Brooklyn

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 01/17/2025