Sunset Park Playground Play Equipment and Safety Surfacing Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will install a Mobius Climber play equipment unit and reconstruct the surrounding safety surface in Sunset Park Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: February 2017
Projected Completion Date: May 2018
Completion Date: December 2017

Procurement

Start Date: May 2017
Projected Completion Date: October 2017
Completion Date: September 2017

Construction

Start Date: September 2018
Projected Completion Date: December 2018
Completion Date: July 2019

Understand how we build parks.

Funding

Total Funding: $97,000
Funding Sources:
  • Mayoral
  • City Council

Location

Sunset Park, Brooklyn

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project