Ocean Breeze Athletic Complex Storefront Doors Reconstruction

  • Design
    100% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will reconstruct the storefront doors at the Ocean Breeze Athletic Complex.

Project Notes

Project Update: Design is complete and permitting and legal review of the contract are in progress.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: June 2024
Projected Completion Date: September 2024
Completion Date: March 2025

Procurement

The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million

Location

Ocean Breeze Park, Staten Island
Quintard Street & Mason Avenue
Community Board: 02

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 03/28/2025