Ocean Breeze Athletic Complex Storefront Doors Reconstruction
-
80% complete
-
0% complete
-
0% complete
This project will reconstruct the storefront doors at the Ocean Breeze Athletic Complex.
Project Notes
Project Update: Parks staff members are reviewing construction documents for this project.
Project Timeline
Design
Assigned & Start Date: June 2024
Projected Completion Date:
September 2024
Procurement
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Location
Ocean Breeze Park, Staten Island
Quintard Street & Mason Avenue
Community Board: 02
Project Staff
Project Liaison: Cristin Leoutsakos
Contact NYC Parks
about this project
Last updated: 11/22/2024