Ocean Breeze Athletic Complex Storefront Doors Reconstruction

  • Design
    80% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will reconstruct the storefront doors at the Ocean Breeze Athletic Complex.

Project Notes

Project Update: Parks staff members are reviewing construction documents for this project.

Project Timeline

Design

Assigned & Start Date: June 2024
Projected Completion Date: September 2024

Procurement

The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million

Location

Ocean Breeze Park, Staten Island
Quintard Street & Mason Avenue
Community Board: 02

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 11/22/2024