Prospect Park Boathouse Reconstruction
-
35% complete
-
0% complete
-
0% complete
This project will reconstruct the boathouse at Prospect Park, including restoring the exterior terracotta tiles, façade, and interior floors, as well as upgrading the electrical service and installing a new HVAC system.
Project Notes
Project Update: The schematic design for this project has been approved. Parks is now developing the documents required to build this project.
Project Timeline
Design
Assigned & Start Date: April 2023
Projected Completion Date:
November 2024
Procurement
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: State
Location
Prospect Park, Brooklyn
101 East Drive
Community Board: 06, 07, 08, 09, 14
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 11/22/2024