St. John's Recreation Center Pool Filter Plant Reconstruction

  • Design
    100% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will reconstruct the pool filter plant at St. John's Recreation Center.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: March 2024
Projected Completion Date: August 2024
Completion Date: July 2024

Procurement

The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $1 million

Location

St. John's Park, Brooklyn
St. John's Recreation center
Community Board: 08

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 11/22/2024