St. John's Recreation Center Pool Filter Plant Reconstruction
-
100% complete
-
0% complete
-
0% complete
This project will reconstruct the pool filter plant at St. John's Recreation Center.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: March 2024
Projected Completion Date:
August 2024
Completion Date:
July 2024
Procurement
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Location
St. John's Park, Brooklyn
St. John's Recreation center
Community Board: 08
Project Staff
Project Liaison: Cristin Leoutsakos
Contact NYC Parks
about this project
Last updated: 11/22/2024