Beach 108 - Beach Channel Drive Sidewalk Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the sidewalks, including drop curbs, steel face curb and a new 4' high chain link fence, from Beach 108th Street to Beach 111th Street along Beach Channel Drive.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: December 2016
Projected Completion Date: January 2017
Completion Date: June 2017

Procurement

Start Date: May 2017
Projected Completion Date: October 2017
Completion Date: August 2017

Construction

Start Date: March 2017
Projected Completion Date: April 2017
Completion Date: April 2017

Understand how we build parks.

Funding

Total Funding: $124,000
Funding Source: Mayoral

Location

Park at Beach 108 Street, Queens

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 10/11/2024