Beach 108 - Beach Channel Drive Sidewalk Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the sidewalks, including drop curbs, steel face curb and a new 4' high chain link fence, from Beach 108th Street to Beach 111th Street along Beach Channel Drive.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: December 2016
Projected Completion Date:
January 2017
Completion Date:
June 2017
Procurement
Start Date: May 2017
Projected Completion Date:
October 2017
Completion
Date:
August 2017
Construction
Start Date: March 2017
Projected Completion Date:
April 2017
Completion Date: April 2017
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Park at Beach 108 Street, Queens
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project
Last updated: 01/17/2025