Wagner Houses Pool Reconstruction

  • Design
    0% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will reconstruct the pool facility.

Project Notes

Project Update: A meeting was held with stakeholders to discuss the scope of work for the project. Parks is now reviewing feedback from the meeting and the scope of work to determine the schedule for the project.

Project Timeline

Design

Assigned & Start Date: July 2024

Procurement

The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Greater than $10 million

Location

Wagner Houses Pool, Manhattan
The east side of Second Avenue, between East 120th Street and East 121st Street.
Community Board: 11

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 10/11/2024