Joseph H. Lyons Pool Partial Reconstruction

  • Design
    0% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will reconstruct the pool deck, diving pool and the filter-plant.

Project Notes

Project Update: A meeting was held with stakeholders to discuss the scope of work for the project. Parks is now reviewing feedback from the meeting and the scope of work to determine the schedule for the project.

Project Timeline

Design

Assigned & Start Date: September 2024

Procurement

The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Source: Mayoral

Location

Lyons Pool, Staten Island
Murray Hulbert Avenue between Victory Boulevard and Hannah Street
Community Board: 01

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 11/22/2024