Jaime Campiz Playground Basketball Courts and Adult Fitness Area Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the basketball courts and adult fitness area in Jaime Campiz Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: June 2016
Projected Completion Date: September 2017
Completion Date: October 2017

Procurement

Start Date: May 2017
Projected Completion Date: September 2017
Completion Date: October 2017

Construction

Start Date: March 2018
Projected Completion Date: July 2018
Completion Date: August 2018

Understand how we build parks.

Funding

Total Funding: $223,000
Funding Sources:
  • Mayoral
  • City Council

Location

Jaime Campiz Playground, Brooklyn

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project