Northern Playground Basketball Court and Handball Court Reconstruction
-
100% complete
-
0% complete
-
0% complete
This project will reconstruct the basketball court, handball courts and add a drinking fountain to the public restroom building at Northern Playground.
Project Notes
Project Update: Design is complete and permitting and legal review of the contract are in progress.
Project Timeline
Design
Assigned & Start Date: December 2023
Projected Completion Date:
December 2024
Completion Date:
December 2024
Procurement
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Mayoral
Location
Northern Playground, Queens
Northern Boulevard and 93rd Street
Community Board: 03
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project
Last updated: 01/17/2025