New York State Pavilion Observation Towers Reconstruction - Phase 2

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    37% complete

This project will reconstruct portions of the New York State Pavilion Observation Towers in Flushing Meadows Corona Park.

Project Notes

Due to COVID related impacts, this project may have experienced schedule delays.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: September 2015
Projected Completion Date: September 2016
Completion Date: April 2018

Procurement

Start Date: April 2018
Projected Completion Date: January 2019
Completion Date: October 2023

Construction

Start Date: October 2023
Projected Completion Date: October 2025

Understand how we build parks.

Funding

Total Funding: $56,756,000

Location

Flushing Meadows Corona Park, Queens
Perimeter Road and United Nations Avenue South
Community Board: 03, 04, 06, 07, 08

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 10/11/2024