Noble Playground Water Service Reconstruction
-
30% complete
-
0% complete
-
0% complete
This project will reconstruct the water tap and water service to the basketball courts at Noble Playground.
Project Notes
Project Update: The schematic design for this project has been approved internally at Parks and is now going through review by the community board and external regulatory agencies for comment and approval.
Project Timeline
Design
Assigned & Start Date: March 2024
Projected Completion Date:
February 2025
Procurement
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: City Council
Location
Noble Playground, Bronx
Noble Avenue, Cross Bronx Expressway, and Bronx River Parkway
Community Board: 09
Project Staff
Project Liaison: Katerine Borrome
Contact NYC Parks
about this project
Last updated: 11/22/2024