Brower Park Basketball Court Bleachers Construction

  • Design
    100% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will install bleachers at the basketball courts in Brower Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: February 2024
Projected Completion Date: August 2024
Completion Date: May 2024

Procurement

The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $1 million
Funding Source: State

Location

Brower Park, Brooklyn
Park Place and Brooklyn Avenue
Community Board: 08

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 11/22/2024