Brower Park Basketball Court Bleachers Construction
-
100% complete
-
0% complete
-
0% complete
This project will install bleachers at the basketball courts in Brower Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: February 2024
Projected Completion Date:
August 2024
Completion Date:
May 2024
Procurement
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: State
Location
Brower Park, Brooklyn
Park Place and Brooklyn Avenue
Community Board: 08
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 11/22/2024