Mullaly Recreation Center Door Replacement
-
100% complete
-
100% complete
-
100% complete
This project will install new entrance doors at Mullaly Recreation Center.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: October 2016
Projected Completion Date:
January 2017
Completion Date:
March 2017
Procurement
Start Date: August 2017
Projected Completion Date:
January 2018
Completion
Date:
February 2018
Construction
Start Date: February 2018
Projected Completion Date:
March 2018
Completion Date: March 2018