Hunts Point Recreation Center Indoor Track and Lift Reconstruction
-
35% complete
-
0% complete
-
0% complete
This project will reconstruct the indoor track and lift at Hunts Point Recreation Center.
Project Notes
Project Update: The schematic design for this project has been approved. Parks is now developing the documents required to build this project.
Project Timeline
Design
Assigned & Start Date: April 2024
Projected Completion Date:
April 2025
Procurement
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Location
Julio Carballo Fields, Bronx
765 Manida Street
Community Board: 02
Project Staff
Project Liaison: Katerine Borrome
Contact NYC Parks
about this project
Last updated: 11/22/2024