Al Oerter Recreation Center Gym Floor Reconstruction
-
5% complete
-
0% complete
-
0% complete
This project will reconstruct the gym floor at Al Oerter Recreation Center.
Project Notes
Project Update: Parks has reviewed stakeholder feedback and the scope of work for this project, and is now developing the design for the site.
Project Timeline
Design
Assigned & Start Date: May 2024
Projected Completion Date:
October 2024
Procurement
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: City Council
Location
Flushing Meadows Corona Park, Queens
131-40 Fowler Avenue
Community Board: 03, 04, 06, 07, 08
Project Staff
Project Liaison: Cristin Leoutsakos
Contact NYC Parks
about this project
Last updated: 11/22/2024