Telephone Playground Reconstruction
-
5% complete
-
0% complete
-
0% complete
This project will reconstruct Telephone Playground.
Project Notes
Project Update: Parks has reviewed stakeholder feedback and the scope of work for this project, and is now developing the design for the site.
Project Timeline
Design
Assigned & Start Date: January 2025
Projected Completion Date:
April 2026
Procurement
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: City Council
Location
Telephone Playground, Queens
LOCATED AT75TH AVENIE BETWEEN BELL BOULEVARD AND 217TH STREET
Community Board: 11
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project
Last updated: 11/22/2024