Juniper Valley Park Multipurpose Play Area Reconstruction

  • Design
    30% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will reconstruct the multipurpose play area at Juniper Park.

Project Notes

Project Update: The schematic design for this project has been approved internally at Parks and is now going through review by the community board and external regulatory agencies for comment and approval.

Project Timeline

Design

Assigned & Start Date: October 2024
Projected Completion Date: January 2026

Procurement

The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $5 million and $10 million
Funding Source: City Council

Location

Juniper Valley Park, Queens
LOCATED AT 80TH STREET BETWEEN JUNIPER BOULEVARD NORTH AND SOUTH
Community Board: 05

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 03/28/2025