Riverside Park South Adult Fitness Equipment Construction
-
0% complete
-
0% complete
-
0% complete
This Project will construct Adult Fitness Equipment in Riverside Park.
Project Notes
Project Update: A meeting was held with stakeholders to discuss the scope of work for the project. Parks is now reviewing feedback from the meeting and the scope of work to determine the schedule for the project.
Project Timeline
Design
Assigned & Start Date: June 2024
Procurement
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: City Council
Location
Riverside Park South, Manhattan
Riverside Park South at West 71st Street
Community Board: 07
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 11/22/2024