Conference House Park Visitor Center Restrooms Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the visitor center restrooms in Conference House Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: November 2015
Projected Completion Date: February 2016
Completion Date: April 2017

Procurement

Start Date: January 2017
Projected Completion Date: July 2017
Completion Date: July 2017

Construction

Start Date: July 2017
Projected Completion Date: November 2017
Completion Date: November 2017

Understand how we build parks.

Funding

Total Funding: $455,000
Funding Source: Borough President

Location

Conference House Park, Staten Island

 

Project Staff

Project Liaison: Joseph Homsey
Contact NYC Parks about this project

Last updated: 11/22/2024