Hallets Point Playground Reconstruction

  • Design
    0% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will reconstruct Hallets Point Playground.

Project Notes

Project Update: A meeting was held with stakeholders to discuss the scope of work for the project. Parks is now reviewing feedback from the meeting and the scope of work to determine the schedule for the project.

Project Timeline

Design

Assigned & Start Date: November 2024
Projected Completion Date: October 2025

Procurement

The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $3 million and $5 million
Funding Sources:
  • Mayoral
  • Private

Location

Hallets Cove Playground, Queens
Astoria Boulevard between 1st Street and the East River
Community Board: 01

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 10/11/2024