Bronx & Manhattan Private Funding Tree Planting FY24
-
90% complete
-
0% complete
-
0% complete
This project will plant new and replacement trees in Bronx and Manhattan with private funding.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: October 2023
Projected Completion Date:
June 2024
Adjusted Completion Date:
June 2025
Procurement
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Last updated: 11/22/2024