Citywide Grow Bag Tree Planting for Bioswales

  • Design
    5% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will plant new and replacement grow bag trees Citywide.

Project Notes

Project Update: Parks has reviewed stakeholder feedback and the scope of work for this project, and is now developing the design for the site.

Project Timeline

Design

Assigned & Start Date: October 2023
Projected Completion Date: October 2024

Procurement

The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $1 million

Location

Various locations

Project Staff

Contact NYC Parks about this project

Last updated: 10/11/2024