Citywide Street Tree Planting Site Preparation FY24

  • Design
    100% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will prepare sites for planting new and replacement trees.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2023
Projected Completion Date: April 2024
Completion Date: February 2024

Procurement

Start Date: February 2024
Projected Completion Date: February 2025
Adjusted Completion Date: April 2025

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $1 million
Funding Source: Mayoral

Location

Various locations

Project Staff

Contact NYC Parks about this project

Last updated: 11/22/2024