Citywide Street Tree Planting Site Preparation FY24

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will prepare sites for planting new and replacement trees.

Project Notes

Project Update: A date has been set for construction to begin.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2023
Projected Completion Date: April 2024
Completion Date: February 2024

Procurement

Start Date: February 2024
Projected Completion Date: February 2025
Completion Date: March 2025

Construction

Start Date: March 2025
Projected Completion Date: March 2026

Understand how we build parks.

Funding

Total Funding: $445,000
Funding Source: Mayoral

Location

Various locations

Project Staff

Contact NYC Parks about this project

Last updated: 03/28/2025