Staten Island Street Tree Planting FY24
-
100% complete
-
40% complete
-
0% complete
This project will plant new and replacement street trees in Staten Island.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: October 2023
Projected Completion Date:
June 2024
Completion Date:
April 2024
Procurement
Start Date: April 2024
Projected Completion Date:
August 2025
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Sources:
- Mayoral
- Private
Last updated: 11/22/2024