Brooklyn Street Tree Planting FY10 - Community Board 2

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will plant new street trees in Brooklyn Community Board 2.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: September 2009
Completion Date: August 2011

Procurement

Start Date: August 2011
Projected Completion Date: May 2012
Completion Date: June 2012

Construction

Start Date: July 2012
Projected Completion Date: July 2013
Completion Date: November 2013

Understand how we build parks.

Funding

Total Funding: $789,000
Funding Source: City Council

Location

Various locations in Brooklyn Community Board 2.