Queens Street Tree Planting FY25 - Community Board 7 & 8
-
90% complete
-
0% complete
-
0% complete
This project will plant new and replacement trees in Community Boards 7-8 in Queens.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: October 2023
Projected Completion Date:
June 2024
Adjusted Completion Date:
June 2025
Procurement
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: Mayoral
Last updated: 11/22/2024