Mahoney Playground Rain Garden Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the rain garden in Mahoney Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: July 2016
Projected Completion Date: November 2016
Completion Date: November 2016

Procurement

Start Date: December 2016
Projected Completion Date: May 2017
Completion Date: June 2017

Construction

Start Date: October 2017
Projected Completion Date: January 2018
Completion Date: April 2018

Understand how we build parks.

Funding

Total Funding: $208,000
Funding Sources:
  • Mayoral
  • City Council

Location

Mahoney Playground, Staten Island

 

Project Staff

Project Liaison: Joseph Homsey
Contact NYC Parks about this project

Last updated: 11/22/2024