Brooklyn Street Tree Planting FY24 - Community Board 7 & 10

  • Design
    100% complete
  • Procurement
    40% complete
  • Construction
    0% complete

This project will plant new and replacement trees in Community Boards 7 & 10 in Brooklyn.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2023
Projected Completion Date: June 2024
Completion Date: April 2024

Procurement

Start Date: April 2024
Projected Completion Date: April 2025
Adjusted Completion Date: July 2025

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $1 million
Funding Sources:
  • City Council
  • Mayoral

Location

Various locations in Brooklyn

Project Staff

Contact NYC Parks about this project

Last updated: 11/22/2024