Queens Street Tree Planting FY24 - Community Board 11-13

  • Design
    100% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will plant new and replacement trees in Community Boards 11-13 in Queens.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2023
Projected Completion Date: April 2024
Completion Date: February 2024

Procurement

Start Date: February 2024
Projected Completion Date: February 2025

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $5 million and $10 million
Funding Sources:
  • Mayoral
  • Private

Location

Various locations in Queens

Project Staff

Contact NYC Parks about this project

Last updated: 10/11/2024