Brooklyn Street Tree Planting FY24 - Community Board 11, 13, 15

  • Design
    100% complete
  • Procurement
    5% complete
  • Construction
    0% complete

This project will plant new and replacement trees in Community Boards 11, 13, 15 in Brooklyn.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2023
Projected Completion Date: June 2024
Completion Date: August 2024

Procurement

Start Date:
Projected Completion Date: October 2025

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Sources:
  • Mayoral
  • Private

Location

Various locations in Brooklyn

Project Staff

Contact NYC Parks about this project

Last updated: 11/22/2024