Gonzalo Plasencia Playground Reconstruction
-
30% complete
-
0% complete
-
0% complete
This project will reconstruct the playground, natural turf field, basketball courts, handball courts, and sitting area in Gonzalo Plasencia Playground.
Project Notes
Project Update: The schematic design for this project has been approved internally at Parks and is now going through review by the community board and external regulatory agencies for comment and approval.
Project Timeline
Design
Assigned & Start Date: September 2024
Projected Completion Date:
December 2025
Procurement
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Gonzalo Plasencia Playground, Brooklyn
41st Street between 3rd and 4th Avenues
Community Board: 07
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 02/21/2025