Central Park and Flushing Meadows Corona Park Electric Vehicle Charging Stations Construction

  • Design
    30% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will remove compressed natural gas (CNG) fuel tanks and construct electric vehicle charging stations at the Central Park 86th Street Shops and Flushing Meadows Corona Park Garage.

Project Notes

Project Update: The schematic design for this project has been approved internally at Parks and is now going through review by the community board and external regulatory agencies for comment and approval.

Project Timeline

Design

Assigned & Start Date: June 2024
Projected Completion Date: June 2025

Procurement

The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $1 million
Funding Source: Mayoral

Location

86th Street Transverse in Central Park and Olmsted Drive and Stadium Place South in Flushing Meadows Corona Park

Project Staff

Project Liaison: Contact Us
Contact NYC Parks about this project

Last updated: 11/22/2024