Wolfe's Pond Park Playground Reconstruction and Pickleball Courts Construction
-
0% complete
-
0% complete
-
0% complete
This project will reconstruct the playground and construct the pickleball courts at Wolfe's Pond Park.
Project Notes
Project Update: A meeting was held with stakeholders to discuss the scope of work for the project. Parks is now reviewing feedback from the meeting and the scope of work to determine the schedule for the project.
Project Timeline
Design
Assigned & Start Date: October 2024
Procurement
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
Location
Wolfe's Pond Park, Staten Island
Cornelia and Chester Avenues
Community Board: 03
Project Staff
Project Liaison: Joseph Homsey
Contact NYC Parks
about this project
Last updated: 11/22/2024