Travers Park Basketball Courts Reconstruction

  • Design
    5% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This Project will reconstruct the basketball courts at Travers Park.

Project Notes

Project Update: Parks has reviewed stakeholder feedback and the scope of work for this project, and is now developing the design for the site.

Project Timeline

Design

Assigned & Start Date: February 2024
Projected Completion Date: February 2025

Procurement

The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Source: Borough President

Location

Travers Park, Queens
This project is located between Northern Boulevard, 34th Avenue, 77th and 79th Streets
Community Board: 03

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 11/22/2024